District 3 Road Projects
Maintenance Projects as of July 2019
|
Project Name |
Scope of Work |
Estimated Completion |
|
161st between Hwy. 75 and Lewis Ave (Chipsealed 2018)
191st between Hwy. 75 and Elwood Ave (Chipsealed 2018)
|
Roadway maintenance, Asphalt Overlay |
On Schedule for 2019 |
|
Peoria from 161st to 181st
|
Roadway maintenance, Asphalt Overlay |
On Schedule for 2019 |
|
145th from Hwy 64 south to 181st Street.
|
Roadway maintenance, Chipseal |
Summer 2019 |
|
Springhill Farms
|
Roadway Rehabilitation |
Begin July 2019 - ongoing project |
|
Mingo, 101st to 111th
|
Roadway maintenance, Asphalt Overlay |
Summer 2019 |
Non-Maintenance Projects as of July 2019
|
Project Name |
Scope of Work |
Design |
Right of Way Access &
Relocation of Utilities
|
Construction |
|
121st Street South between US Hwy 75 and Elwood Avenue
|
Roadway improvements, bridge widening and replacement, and intersection widening and signalization. |
Winter 2018 |
2020 |
2021 |
|
171st Street South between 137th and 161st East Avenue
|
Roadway rehabilitation |
Spring 2018 |
Fall 2020 |
2021 |
|
161st East Avenue between 171st and 181st St. So.
|
Roadway rehabilitation |
Spring 2018 |
Fall 2020 |
2021 |
|
Posey Creek Bridge on Harvard Avenue
|
Bridge replacement |
Spring 2019 |
Summer 2020 |
2020 |
|
Garnett Road between 91st and 101st St. So.
|
Road widening, intersection improvements and signalization |
Under way |
Under way |
2020 |
|
101st Street South between Memorial Drive and Garnett Road
|
Road widening, intersection improvements, signalization, bridge replacement |
Fall 2018 |
Fall 2019 |
Spring 2020 |
|
Bridge on 201st St. So. between Memorial & Mingo
|
Bridge replacement |
Under way |
Fall 2019 |
Winter 2019 |
|
Mingo between 101st and 111th
|
Roadway rehabilitation |
Under way |
Under way |
Completed Summer 2019 |