    ROAD PROJECTS

Tulsa County maintains more than 700 miles of road and nearly 200 bridges. They are the backbone of our neighborhoods, business and education areas. Every municipality in Tulsa County benefits from the Tulsa County Maintenance Master Plan.

County road maintenance projects are sought out, organized and implemented in 2 year cycles. A project that is generated and detailed one year will generally be completed within the following 2 years. It is to be understood that all project scheduling is dependent on weather, budgets, manpower and other extenuating circumstances. Estimated completion dates are goals and subject to change based on road maintenance emergencies.

 


District 3 Road Projects

Maintenance Projects as of July 2019

Project Name Scope of Work Estimated Completion
161st between Hwy. 75 and Lewis Ave (Chipsealed 2018)
191st between Hwy. 75 and Elwood Ave (Chipsealed 2018)
Roadway maintenance, Asphalt Overlay On Schedule for 2019
Peoria from 161st to 181st Roadway maintenance, Asphalt Overlay On Schedule for 2019
145th from Hwy 64 south to 181st Street. Roadway maintenance, Chipseal Summer 2019
Springhill Farms Roadway Rehabilitation Begin July 2019 - ongoing project
Mingo, 101st to 111th Roadway maintenance, Asphalt Overlay Summer 2019

Non-Maintenance Projects as of July 2019

Project Name Scope of Work Design Right of Way Access &
Relocation of Utilities
Construction
121st Street South between US Hwy 75 and Elwood Avenue Roadway improvements, bridge widening and replacement, and intersection widening and signalization. Winter 2018 2020 2021
171st Street South between 137th and 161st East Avenue Roadway rehabilitation Spring 2018 Fall 2020 2021
161st East Avenue between 171st and 181st St. So. Roadway rehabilitation Spring 2018 Fall 2020 2021
Posey Creek Bridge on Harvard Avenue Bridge replacement Spring 2019 Summer 2020 2020
Garnett Road between 91st and 101st St. So. Road widening, intersection improvements and signalization Under way Under way 2020
101st Street South between Memorial Drive and Garnett Road Road widening, intersection improvements, signalization, bridge replacement Fall 2018 Fall 2019 Spring 2020
Bridge on 201st St. So. between Memorial & Mingo Bridge replacement Under way Fall 2019 Winter 2019
Mingo between 101st and 111th Roadway rehabilitation Under way Under way Completed Summer 2019